Monday, July 18, 2011

Getting close . . .





















With the move in date just a month or so away, the campus is starting to have some finishes applied. The installation of the mechanical system is pretty much finished, most of the drywall is up, some of the flooring is down. The floors are going to be polished concrete, marmoleum (a product made with linseed oil and hence a sustainable product) and cork.



On the mechanical room mezzanine the electrical panels are in and the grey water collection system in place. The grey water will be used to flush toilets to reduce our environmental impact.






















The duct work along the walls is covered with beautiful maple that matches the doors, the kitchen cabinetry is installed, the tiles are going up in the washrooms.






















Outside, the entrances all have doors now, and the landscaping work is underway.

Friday, July 1, 2011






Our occupancy date has been moved back to August 15, which is cutting it pretty close for the start of classes. But my tour this week showed that some of the spaces really are close to being ready for our big move-in -- the classrooms, the offices, and the masonry shop.



The cable is being pulled in the computer lab, the walls are painted, and workers were sanding the floors to prepare them for the marmoleum. Who knew that good old linoleum is one of the greenest floor products around, made from linseed oil?

The masonry shop has been brightened up with a coat of paint, and you can begin to appreciate how big it is. The extra height will allow the students to use scaffolds inside and build larger, more interesting projects in the dead of winter. There are chimneys, too, so that the fireplaces they build can be fired and tested.

The progress on the mechanical system is most evident in the cafeteria, where a bulkhead has appeared in the last week. Plumbing is starting to appear in the washrooms, too. And the framing for the doors and windows in the Students Association areas is in.


Some of the interior windows and doors have been installed. In the new building, guests to the campus will be able to take a look into both the joinery and the masonry shop to see our students in action.

The main entrance is almost complete -- the canopy is shingled, and the masonry accents are being applied. The exterior of the trades wing will have the final touch of the wood siding completed by next week.

Friday, June 10, 2011

Indoor spaces starting to be defined





















President Gillett, Director of Physical Resources Mike Rushton, Head of Major Construction John Dalziel, and Architect John Cook toured the Perth Campus construction site yesterday. The interior spaces are starting to take shape -- the shops have walls, acoustic block features, and all of the floors are poured. Drywall is up for most of the offices and classroom spaces, and some of it is painted already. Outside, there is a mock-up of the masonry finish showing how the siding and masonry accents will work together. You can see the mechanical system installations moving forward quickly too.

Tuesday, May 10, 2011

Construction site is hopping now that spring is here













We took the fundraising campaign cabinet on a tour of the site today. There were skilled tradesworkers of all descriptions there -- drywallers, roofers, electricians, hvac specialists. There is drywall on most of the walls now; the carpentry shop has a floor and the masonry half wall is up. You can really see how the light will brighten up the entrance and the hallways and how comfortable it will be in the cafeteria.

Monday, May 2, 2011

Dust Collection System Arrives













Today was a busy day on the construction site -- there were insulation installers, window and door installers and, most exciting of all -- the arrival of the new dust collection system for the shops, which looks remarkably like a rocket ship going up.

Friday, April 29, 2011

Getting ready for our dust collection



Today they were pouring the pad for a new dust collection system for our carpentry and masonry shops.

Inside work underway













The electrical and mechanical system work has been progressing. Some drywall is going up.

Monday, April 18, 2011

Today's progress



Some of the shots I took today show how the building will meet the needs of the occupants -- with lots of light, windows that open, and space for students to meet and hang out between classes.

Building Progressing!




I haven't posted for some time because I was away from the campus working on an International program.


In February, the campus staff and faculty had the opportunity to go on a tour of their new home and seemed quite pleased with the work in progress.

Monday, February 14, 2011

Bursary Donors Go on Tour of New Building




On Thursday, February 10, the annual Donor Bursary Awards Ceremony took place at the Perth Campus. Generous donors gave out $15,000 in bursaries to 30 students at Perth who met their criteria and demonstrated financial need. After the ceremony, we gave them a tour of the new facility. It's close to being closed in, with most walls framed, window frames installed in most openings, and the last of the complicated roof truss sytem going up.

Friday, February 4, 2011

Roof On the Trades Building




In the past week, some framing inside the new building has taken place, and you can see clearly where the new student fitness centre will be, the layout of the adminstrative area, and the cafeteria and student lounge. The trades building is all closed in now, with the roof in place and the mezzanine level visible.




Friday, January 28, 2011

Construction in January




The construction crews continue to work around the challenges of cold, snow and the Canadian winter. The final group of roof trusses are going up on the student commons. Some interior work is being finished in the academic wing. The natural gas connections are in place. The roof deck and much of the roof is finished now on the trades building. Those sections of the trades building that look unfinished will be covered with wood siding for now, and eventually with masonry work completed the the Heritage Masonry program students.


Friday, January 21, 2011

Cold week for roofing.


Most days were clear and crisp this week, but the roofers looked pretty cold. Earlier today, the crew putting shingles on the roof had leaf blowers out -- blasting the snow off so they could put more shingles down.

Friday, January 14, 2011

Student Commons Trusses Go Up




At the end of this week, the roof trusses which had been assembled on the ground, started to go up over the administrative offices and student commons area (library, cafeteria, student lounge). Now the complete building shape is visible.




Crews worked all week on the trades building, too, getting it ready for roofing.

Thursday, January 6, 2011

Holiday Progress











While staff and students of the College were taking an end of semester break, work continued on the new campus, with insulation being added to the walls of the academic wing, shingling taking place on the same wing, and ongoing work on the structure for the trades building.